Chamberlain Hall construction September update



The construction works at Chamberlain Hall continue to progress with the first building frame completed.  The roof blocks of Block C have been installed and work will now move onto the other two linear blocks next week with a large crawler crane coming to allow work on one of the blocks.

The first of the main slabs on the tower block is due to be poured at the beginning of next week.  Next week will also see the installation of the shower pods into the bedrooms 

The photos below show how work has progressed since my last update of 19 August, http://birminghamcentral.blogspot.com/2014/08/chamberlain-hall-construction-august.html