Edgbaston Cricket Ground redevelopment - February update

Progress on the redevelopment of Edgbaston Cricket Ground continues since my previous update, Edgbaston Cricket Ground redevelopment - January update.

Steelwork erection on the new entrance which includes the main banqueting room continues as shown in the pictures below.

31st January 2010


1st February 2010


Edgbaston Cricket Ground's website update on the work, http://www.edgbaston.com/news/latest-development-update/, informs us that the cladding on Edgbaston Road frontage is now complete, all of the terracing is complete and a large part of the glazing has been installed, re-turfing is substantially complete and 4 of the 5 floodlights have now been erected with the 5th scheduled to be erected in the middle of February.

The new stand from inside the ground, reproduced from Edgbaston Cricket Ground website: http://www.edgbaston.com/news/latest-development-update/